1. Construction Overview
The first drilling operation in the TaLiMu Well using the reamer + PV reaming-while-drilling assembly began at 20:00 on October 26, 2019, and ended when the reamer and bit returned to surface at 10:00 on November 13, 2019.
Total section completed: 790 m
Pure drilling time: 212 h
Average ROP: 3.72 m/h
Total circulation time: 298 h
The reamer maintained good working condition throughout the entire run.
2. Reaming Operation Summary
Basic Operating Data
Drilling interval: 6235–7045 m
Reamed interval: 6223–7013 m
Formation: Kumglemu Group
Lithology: salt rock, mudstone, gypsum
Drilling Parameters
WOB: 3–8 T
RPM: 60–80
Torque: 6–15 kN·m
Flow rate: 23–25 L/s
Pump pressure: 28–31 MPa
Mud Properties
Density: 2.35 g/cm³
Viscosity: 72–76 s
3. BHA & Tool Performance
A 9.5″ × 10.5″ hydraulic reamer specifically designed for salt formations was used.
Total run duration:
Pure drilling: 212 h
Total downhole time: 298 h
Performance results:
Reamer condition: no tooth loss or damage
Bit condition: intact, minimal wear
Rating: 1-1-WT-A-X-X-X-0-NO-BHA
The tool successfully expanded the 9-1/2″ hole to 10-1/2″ in a single trip.
4. Operational Achievements
This operation represents:
The first reaming-while-drilling trial in the Tarim Oilfield
The first successful hydraulic reamer application in salt-formation sections of the Kumglemu Group
Key performance highlights:
Successfully activated at 6256 m
Reamed through the gypsum interval at 7045 m
Zero downhole or personnel incidents
Total reaming time: 231 h
Downhole temperature: static ~150°C, circulating ~145°C
5. Technical Benefits Observed
Compared with conventional PDC drilling:
No significant increase in torque or drilling time in the salt formation
Average ROP in salt: 9–11 m/h
Improved tripping efficiency—no sticking or obstructions
Reduced non-productive time
Enlarged borehole minimised formation creep risks
6. Conclusion
The successful application in Well Keshen-17 provides valuable operational experience for safe and efficient drilling in the salt formations of the Kumglemu Group within the Keshen Piedmont block. It demonstrated high-quality execution, operational safety, and set a new performance benchmark.